From the office of state Sen. Bob Cassilly:
The Maryland State Highway Administration has provided my office with an update on the ongoing construction on Rte 755 in Edgewood. The project has experienced several unpredictable utility delays. The contractor is scheduled to return to work in early October to continue with the remaining storm drain installation and roadway widening. Under the current schedule, the project should be completed in midsummer 2016 (weather permitting). The remaining steel plates will be removed and patched before this winter. Flagging operations will manage traffic as construction continues.
If you have any questions, please feel free to contact my office at:
(443) 502-0583 or Bob.Cassilly@senate.state.md.us
none says
OSHA and MOSHA need to investigate the contract for allowing his workers to in the trenches with out any shoring boxes. Someone will die on that job if something isn’t done.